Glossary
Smart Export Guarantee (SEG): how it works and who qualifies
How the Smart Export Guarantee pays for solar you export: who qualifies, the MCS and meter rules, what suppliers pay now, and why plug-in solar usually can't.
SEG at a glance
- domestic customers: suppliers this size must offer SEG
- 150,000
- largest eligible installation
- 5 MW
- the only floor on the rate
- > 0p
What is the Smart Export Guarantee?
The Smart Export Guarantee is a GB scheme, set up by the Smart Export Guarantee Order 2019, under which electricity suppliers pay small low-carbon generators for the electricity they send to the grid. It replaced the export payments of the Feed-in Tariff, which closed to new applicants in 2019, and Ofgem administers it (gov.uk).
It’s a guarantee that a tariff exists, not a guaranteed rate. Larger suppliers must offer at least one SEG tariff, but each chooses its own price and terms. Ofgem says the only rule on price is that “any SEG tariff offered must always remain above zero” (Ofgem).
Who has to offer it
“Licensed electricity suppliers with at least 150,000 domestic electricity customers are required to offer at least one SEG compliant tariff… Other suppliers may participate on a voluntary basis” (Ofgem guidance).
You don’t have to sell your export to the company that supplies your electricity. Many suppliers do pay their own customers more, though.
Who qualifies
Your installation needs all of these (Ofgem):
| Requirement | What Ofgem says |
|---|---|
| Technology | Solar PV, wind, hydro, anaerobic digestion or micro-CHP |
| Size | “No more than 5MW, or no more than 50kW for micro-CHP” |
| Location | Great Britain |
| Certification | For solar PV, wind and micro-CHP up to 50 kW, the installation and installer certified through MCS or an equivalent scheme |
| Metering | A meter “capable of taking half-hourly measurements”, with an export MPAN |
Without the certification, the supplier “is not obliged” to pay you, “but they can make payments if they wish” (Ofgem guidance). The export MPAN is a separate number from the one you buy electricity on; see MPAN.
Batteries
If a battery is charged from the grid as well as from your panels, the supplier can’t tell which exported units came from the sun. Ofgem says that where the export meter also records “a battery that is charged from a source other than the SEG eligible technology”, the supplier isn’t obliged to pay for that export. It may pay anyway, pro-rate the payment or ask for extra meters.
How much SEG pays
Rates vary a lot, and many suppliers pay their own customers more. What suppliers’ own pages said when we checked on 10 November 2026:
| Supplier and tariff | Rate | Who can get it |
|---|---|---|
| Octopus: Outgoing Octopus | 12p/kWh | Octopus electricity customers |
| Octopus: Smart Export Guarantee | 4.1p/kWh | Anyone, including other suppliers’ customers |
| British Gas: Export Premium | 12p/kWh | British Gas customers, systems up to 15 kW |
| British Gas: Export SEG | 3p/kWh | Other suppliers’ customers |
| EDF: Export Variable Value | 5.6p/kWh | EDF customers |
| EDF: Export Variable | 2p/kWh (from 28 Oct 2026, down from 3p) | Anyone |
Sources: Octopus, British Gas, EDF. Each still needs an MCS (or equivalent) certificate and a half-hourly meter. Rates change, so check the supplier’s page before you sign up.
Compare that with what you pay to buy electricity: 26.32p per kWh on average under the Ofgem price cap for October to December 2026. A unit you use yourself saves that full rate, several times what an open SEG tariff pays for a unit you export, which is why self-consumption matters more than the export rate for small systems.
How to apply
- Get the paperwork from your installer: the MCS certificate and the network operator’s confirmation under G98 or G99.
- Make sure you have a smart meter that records half-hourly export. Your supplier can fit one.
- Choose a SEG tariff. Compare your own supplier’s rate with the open-to-anyone rates above.
- Apply to the supplier. It arranges the export MPAN with your network operator. Octopus says this “usually takes between one and four weeks”.
Plug-in solar and SEG
Most plug-in kits can’t get SEG. They’re designed to be fitted by the householder, so there’s no MCS installer or certificate. DESNZ’s impact assessment says that “without an MCS-accredited installation of domestic solar consumers are not entitled to the Smart Export Guarantee in Great Britain” (para 61).
Nothing in the 2026 plug-in solar law or the July 2026 government response changes that. Consultation respondents asked for “Smart Export Guarantee reform”, but the government made no commitment on it.
Any payment for plug-in export is a supplier’s own offer, outside the scheme’s guarantee. In November 2026:
- Octopus pays export on plug-in kits it sold, to its own electricity customers with a working smart meter, once the kit is registered and the network operator approves it (Octopus).
- British Gas lists plug-in solar export as “coming soon” (British Gas).
Our plug-in solar export guide works out how much a typical kit exports and what that would be worth. The calculator values export at zero unless you enter a rate you’ve confirmed.
How plug-in kits limit what you export
A plug-in kit’s output is capped at 800 W by law, but there’s no cap on how much of that leaves your home: whatever you aren’t using flows out to the grid. See export limitation for how the limits work for plug-in, rooftop and battery systems.
Questions
What is the Smart Export Guarantee?
A GB scheme that makes larger electricity suppliers offer at least one tariff paying small low-carbon generators, such as home solar panels, for the electricity they send to the grid. It replaced the export part of the Feed-in Tariff, and suppliers set their own rates.
Who has to offer a SEG tariff?
Licensed electricity suppliers with at least 150,000 domestic customers must offer at least one SEG tariff. Smaller suppliers can offer one voluntarily. You don't have to take your export tariff from the supplier that sells you electricity.
Do I need MCS to get the Smart Export Guarantee?
For solar PV up to 50 kW, yes or an equivalent. Ofgem's guidance says both the installation and the installer must be certified, through the Microgeneration Certification Scheme (MCS) or a scheme accredited as equivalent. Without it a supplier isn't obliged to pay you, though it can choose to.
How much does the Smart Export Guarantee pay?
Each supplier sets its own rate, and the only rule is that it must be above zero. When we checked on 10 November 2026, open-to-anyone SEG rates ran from 2p (EDF) to 4.1p per kWh (Octopus), with higher rates of up to 12p for each supplier's own customers.
Can plug-in solar get the Smart Export Guarantee?
Usually not. Plug-in kits are fitted by the householder, so there's no MCS installation. DESNZ says that without an MCS-accredited installation, domestic solar consumers aren't entitled to SEG. Octopus pays for export only on plug-in kits it sold, to its own customers.
What meter do I need for SEG?
One that can record half-hourly export readings, which in practice means a smart meter, plus an export MPAN for the meter point. Your supplier arranges the export MPAN with the network operator.
Does SEG pay for electricity exported from a battery?
Not necessarily. If the export meter also records a battery charged from the grid, Ofgem says the supplier isn't obliged to pay for that export. It can pay, pro-rate the payment or ask for extra metering.
Sources
- Ofgem: Smart Export Guarantee for generators
- Ofgem: Smart Export Guarantee guidance for generators
- The Smart Export Guarantee Order 2019 (SI 2019/1005)
- gov.uk: Smart Export Guarantee
- DESNZ plug-in solar final-stage impact assessment
- DESNZ plug-in solar government response, July 2026
- Octopus Energy: Smart Export Guarantee tariff
- Octopus Energy: plug-in solar
- EDF: smart export tariffs
- British Gas: Smart Export Guarantee tariffs