minisolar
Stock alertsAlerts

Glossary

Export limits: how much solar power you can send to the grid

How much solar power a UK home can export: the 3.68 kW G98 limit, G99 approval above it, G100 export limiters and the 800 W cap on plug-in solar.

The numbers that set export limits

G98 limit on a single-phase supply (16 A)
3.68 kW
G98 limit on a three-phase supply
11.04 kW
most a plug-in solar kit can output
800 W

What is export limitation?

Export limitation means restricting how much power a home sends out to the grid. A meter or clamp measures the flow at the supply point, and the system turns the inverter down, or diverts surplus into a battery, so net export stays under a set level. “Zero export” is the strictest version: nothing leaves the property.

It’s different from limiting how much a system generates. A home with 6 kW of panels and a 3.68 kW export limit can still use all 6 kW itself. Only the surplus beyond the limit is lost.

How much solar can you export without approval?

The network rules for small generators are set by the Energy Networks Association’s engineering recommendations. G98 covers micro-generators “up to and including 16 A per phase”, which “corresponds to 3.68 kilowatts (kW) on a single-phase supply and 11.04 kW on a three-phase supply” (ENA G98).

Under G98 you, or your installer, notify the network operator “before the time of commissioning or no later than 28 days (inclusive of the day of commissioning) after commissioning”. You don’t need permission first. G98 says this single-premises route doesn’t apply if other installations are planned in the same close area within 28 days.

Most UK homes have a single-phase supply, so 3.68 kW is the number that matters for most rooftop systems.

Above 3.68 kW: G99 and export limits

For anything over 16 A per phase, “the EREC G99 process applies and the DNO needs to be consulted before the installation is undertaken” (ENA G98). The network operator checks whether the local network can take the extra power, and can approve, refuse or approve with conditions.

A common condition is an export limit. SSEN’s fast-track process, for example, sorts single-phase applications into bands: up to 16 A (3.68 kW), up to 32 A (7.36 kW) and up to 60 A (14.72 kW). For the 32 A band it says “an EREC G100 Export Limitation Scheme may be required, limiting export to 16A (3.68kW)”, and “you cannot connect until you receive confirmation that our assessment is complete” (SSEN).

That’s how many homes fit more than 3.68 kW of panels, or panels plus a battery: the system is bigger, but export is held to 3.68 kW.

How G100 export limitation schemes work

ENA’s G100 covers schemes that “limit the net site export to below an agreed maximum”, installed on the customer’s side of the connection. In outline:

  • A sensor at the incoming supply measures whether the home is importing or exporting.
  • When export nears the limit, the controller turns the inverter down or sends the surplus to a battery.
  • It must bring export back under the limit within 5 seconds.
  • It must fail safe: if a sensor or its connection is lost, export has to stop rather than run over the limit. Inverter makers publish G100 declarations showing this.

Many hybrid inverters have export limiting built in, and the installer sets the limit the network operator approved.

Plug-in solar: an 800 W output cap

Plug-in solar is limited in a different way. The law caps the device’s total output: a plug-in microgenerator must have “a maximum rated alternating current output not exceeding 800 watts” (SI 2026/848), and the product specification sets 800 VA and 3.5 A (IPS §4.1).

There’s no export limiter. Whatever your home isn’t using at that moment flows out through your meter to the grid. A kit with more than 800 W of panels doesn’t export more; the inverter caps the output and the extra is clipped.

Plug-in solar kitRooftop solar under G98Rooftop solar under G99
What’s limitedTotal AC outputTotal outputExport, by agreement
Limit800 W16 A per phase (3.68 kW single-phase)Set by the network operator
Before connectingRegister with your DNONotify within 28 daysApproval first
Who installsYouInstallerInstaller

Do you get paid for what you export?

Only with an export tariff. The Smart Export Guarantee needs an MCS-certified installation and a half-hourly meter (Ofgem), so plug-in kits usually don’t qualify. For plug-in solar, the way to get value from surplus is to use more of it: run the washing machine and dishwasher in daylight, and size the kit to your daytime use. Our export guide shows how much a typical kit sends to the grid.

Questions

How much solar power can I export to the grid in the UK?

Without asking your network operator first, up to 16 A per phase under G98: 3.68 kW on a normal single-phase home supply, or 11.04 kW on three-phase. Above that, G99 applies and you need the network operator's approval before you connect, which may come with an export limit.

What is the 3.68 kW limit?

It's 16 A at 230 V, the most a type-tested micro-generator can connect on a single-phase supply under ENA's G98 rules with only a notification to the network operator, given within 28 days of commissioning. Bigger systems go through G99.

Can I install more than 3.68 kW of solar panels?

Yes. Above 16 A per phase the G99 process applies and the network operator must be consulted before installation. Network operators often approve larger systems on condition that a G100 export limitation scheme keeps export to 3.68 kW.

What is a G100 export limitation scheme?

Equipment on your side of the meter that measures how much your home is exporting and turns generation down (or charges a battery) so net export stays under an agreed limit. ENA's G100 sets the rules, including cutting export back within 5 seconds.

How much can a plug-in solar kit export?

Up to its output, which the law caps at 800 W of AC. There's no separate export cap: whatever your home isn't using at that moment flows out to the grid, usually unpaid.

Does export limiting reduce how much solar I generate?

It can. When your home and battery can't use the surplus, the inverter turns down, and that power is lost. It only matters on sunny days when output is high and use is low.

Sources

  1. ENA EREC G98 Issue 2 (March 2025)
  2. ENA EREC G99 Issue 2 (March 2025)
  3. ENA EREC G100 Issue 2 Amendment 1 (July 2022; later amended in 2023)
  4. SSEN: G99 fast track process
  5. SI 2026/848
  6. DESNZ Plug-in Solar Device Interim Product Specification, v2.0
  7. Ofgem: Smart Export Guarantee for generators