The GB network rules for connecting small generators, including plug-in solar kits, in parallel with the local electricity network.

Engineering Recommendation G98 (EREC G98) is the industry rulebook for connecting small generators, up to 16 A per phase, to the electricity network in Great Britain. It covers how the equipment is type-tested and how the local network operator is told about it.

G98 Issue 2 Amendment 1 added a “Plug-in Micro-generator” category: a generator with a registered capacity of 800 W or less, fitted with a standard plug. Ofgem approved the change on 11 August 2026, and it took effect with the plug-in solar law on 27 August 2026 (Ofgem decision).

For plug-in solar, G98 matters in three ways:

In practice: register your kit before you plug it in, or within 28 days of doing so.

Sources

  1. Ofgem decision approving DCRP/MP/26/02 (G98 Issue 2 Amendment 1), 11 Aug 2026
  2. DESNZ Plug-in Solar Device Interim Product Specification, v2.0
  3. DESNZ plug-in solar final-stage impact assessment